A higher permit only helps a plant that’s already running full.
On October 20, 2026, FERC proposed a rule that would let LNG plants raise their authorized capacity within their footprint on 60 days’ notice, unless someone protests. FERC wants comments by December 21.
EIA’s monthly export data shows who would gain.
Plaquemines exported above its old FERC limit in every month from February to July 2026, according to EIA, while its second phase was still commissioning.
Calcasieu Pass, also cleared to export more, didn’t exceed its old limit in any of those months, by the same data.
One plant used the headroom. One didn’t.
FERC isn’t promising much more than that. Its own analysis says the rule would move a handful of projects a year off case-specific review and wouldn’t change how many plants get built.
State attorneys general had already objected to blanket treatment of capacity expansions in January 2026, in comments on FERC’s earlier inquiry.
So what decides the build-out? Probably the next round of investment decisions.
Policy2050’s report estimates that U.S. export liquefaction construction absorbed $25.2 billion of capital in 2025. In the report’s base case, annual spending peaks in 2027 and falls to $20.3 billion by 2030. That drop isn’t a market shrinking, it’s the 2025 wave of projects getting finished, and the report’s base case has nominal export capacity more than doubling over the same years.
New export terminals take most of today’s spending, according to the report. Their spending falls as they’re completed.
New trains (a train is one liquefaction unit) at existing sites or sites still under construction are the only route whose spending holds up to 2030 in the base case, and only if two expansions still waiting on final investment decisions go ahead in 2027, the report finds.
Building next door didn’t come cheaper, either.
In the two 2025 investment filings the report compares, Sempra’s Port Arthur Phase 2, beside a terminal still under construction, showed no visible capital discount per tonne against Woodside’s Louisiana LNG, a new terminal. The discount the Oxford Institute for Energy Studies found for that kind of build in 2018 shows up in neither filing, according to the report.
For developers, lenders, and gas producers, that’s a reason to keep two numbers apart. The capacity that makes LNG. The capacity that’s only permitted.
From 2030, most of the report’s base-case spending rests on decisions not yet made.
The terminal-by-terminal test against FERC and DOE limits, spending by route and state, and three scenarios to 2035 are in the report U.S. LNG Export Liquefaction Market, 2025–2030, on the report’s page.